垃圾焚烧发电厂垃圾池施工方案探讨

来源 :武汉大学学报(工学版) | 被引量 : 0次 | 上传用户:edward109
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
垃圾池为垃圾焚烧发电厂主厂房最主要的结构组成部分,外型体积一般比较大,深度最深,而且一般处于厂房中部,四周均有其他建筑物.天津滨海垃圾焚烧发电厂垃圾池工程施工中,为达到垃圾池和四周建(构)筑物同时施工、节约工期的目的,经过研究,确定了钢板桩+支撑+井点降水的土方开挖支护方案、垃圾池基础底板施工方案、垃圾池上部池壁施工方案,经过施工验证,确保了施工的安全、质量和进度,同时经济效果较好. Garbage dump is the main structural component of the main plant of MSW incineration plant. The appearance volume is generally larger and the depth is the deepest, and it is generally located in the middle of the plant with other buildings all around. Tianjin Binhai MSW Plant Garbage Tank Project , In order to achieve simultaneous construction of rubbish pools and surrounding structures and save time, the earthwork excavation and support scheme of steel sheet pile + support + well point precipitation, the construction plan of garbage basal foundation floor, rubbish The pool upper wall construction program, after construction verification, to ensure the construction safety, quality and progress, at the same time, the economic effect is better.
其他文献
功能翻译理论采取多维的评价标准检验具体的翻译结果.根据对这些多维的评价及时总结功能翻译理论中存在的问题并试图解决,从而拓展功能翻译理论.该理论对中国和东南亚各国之