一、导流规划和导流标准 (一)导流规划铜街子水电站施工导流规划与水工枢纽布置密切相关。最初曾推荐左岸厂房底板及河床溢流坝缺口交替过水的分期围堰导流方案。提出左岸新华乡台地碎石土边坡稳定问题后,水工建筑物右移,作为替代,在左岸滩地上设置导流明渠,导流方式改为断流围堰明渠全年导流。导流平面布置见图1。
First, the diversion planning and diversion standards (a) diversion planning Tongjiezi Hydropower Station construction planning and hydraulic junction layout is closely related. Originally, a diversion scheme was proposed for staged cofferdam in which left-bank plant floor and riverbed spill breach alternate with water. After the issue of stability of the gravel soil slope on the left bank of Xinhua Township on the left bank was made, the hydraulic structure was moved to the right. As an alternative, a diversion channel was set up on the beach of the left bank, and the diversion method was changed to diversion cofferdams. Diversion layout shown in Figure 1.