论文部分内容阅读
针对鹤煤矿区深部开采排水系统已出现的泵房巷道变形、损坏排水部件等问题,原有的泵房排水系统布置方式不能适应深部开采过程中的复杂地质条件,在水泵房排水系统设计初期,对即将可能出现的问题采取有针对性的优化措施,预先防范。通过对三矿-800 m泵房排水系统优化后,未再出现严重影响排水的问题。对于深部排水系统优化布置,有一定的借鉴意义。
In view of the problems such as deformation of the pump house roadway and damage to the drainage components that have occurred in the deep mining drainage system in Hepu coal mine, the existing pumping system drainage system layout can not meet the complicated geological conditions in the deep mining process. In the initial design of the drainage system of the pump house, Targeted optimization measures will be taken for the impending problems and precautionary measures should be taken. After optimizing the drainage system of the 800m pumping station in the Third Mines, there is no recurrence of serious problems of drainage. For the deep drainage system optimization layout, there is a certain reference.