目前,煤矿井下采区基本控制导线,一般采用在棚子上打上木楔,把导线钉钉在木楔上,用白粉抹上,就可以作为测点用了,但这样的固定方法,受放炮震动,扒装时棚梁错动,棚腿失脚等因素影响时,势必严重影响测量精度.现介绍一种用快于水泥在不同巷道施工中固定导线测点的简易方法.其使用要点为:1 棚梁支护在棚梁上面贴着顶板,打个木楔,把测钉或小钉钉在木楔上,然后把快于水泥抹在木楔和顶板的结合部,木楔两侧略包水泥.5min后便可凝固,40min至1h后,就能经得起掘进放炮时煤岩块打击.即使出现倒棚,也不影响测点精度.
At present, the basic control of coal mine underground mining lead wire, the general use of the wedge in the shed on the wedge, the wire nails in the wedge, with white powder, you can use as a measuring point, but such a fixed method, blasting blasting , When the loading and unloading Grillage beams when moving, shed legs and other factors, it is bound to seriously affect the measurement accuracy.A description of a faster than cement in different tunnel construction fixed wire measuring point of a simple method.The use of points: 1 Beam support beam in the shed above the top plate, make a wooden wedge, nail or nail nail in the wedge, and then wipe the cement faster than the wedge and the roof of the junction, wedge slightly on both sides of the package After 5min, the cement can be solidified, and after 40min to 1h, it can withstand the cracking of coal rock blocks during the blasting operation.