论文部分内容阅读
杰克逊市的 J.H Fewell 水处理厂是一个具有复杂的管网输送系统和70年以上发展历史的老厂。它建于1914年,原处理能力为400万加仑/日(15146.4米~3/日),水厂经数年扩建,已使其处理能力提高到5200万加仑/日(196841.32米~3/日)。水厂的基本流程为:混凝、沉淀,和快速砂滤。地表水源取自水厂邻近的珍珠河。1961年,水厂上游12英里远的 Ross Barnett 水库建成。尽管水库上游的珍珠河流域的水大部分用于农业和森林
The J.H Fewell Water Treatment Plant in Jackson City is an old factory with a complex pipe network transmission system and more than 70 years of development history. It was built in 1914. The original processing capacity was 4 million gallons/day (15146.4 meters to 3/day). After several years of expansion, the water plant has increased its processing capacity to 52 million gallons/day (196841.32 meters~3 days). ). The basic flow of a water plant is: coagulation, sedimentation, and rapid sand filtration. Surface water is taken from the Pearl River near the water plant. In 1961, the Ross Barnett Reservoir was built 12 miles upstream of the water plant. Although most of the water in the Pearl River basin upstream of the reservoir is used for agriculture and forestry