根据串列加速器升级工程的进度计划,在2012年期间,100MeV强流回旋加速器水冷系统取得了显著进展。主要包括以下内容。1)完成了7个配水柜的内部接线。2)通过市场调研、竞争性谈判,确定了水冷循环水机和去离子水生产装置的生产厂家,并于2月初签订了制造合同。其中,去离子水生产装置已于5月底完成加工,循环水机于10月中旬完
According to the schedule of the tandem accelerator upgrade project, significant progress has been made in the water cooling system of the 100 MeV high-pressure cyclotron during 2012. Mainly includes the following content. 1) The internal wiring of the seven distribution cabinets is completed. 2) Through the market research and competitive negotiation, the manufacturer of water-cooled circulating water machine and deionized water production equipment has been identified and a manufacturing contract has been signed in early February. Among them, the deionized water production plant has been completed by the end of May processing, circulating water machine in mid-October End