论文部分内容阅读
本文详细介绍了清江高坝洲水电厂计算机监控系统从国外CEGELEC系统改造为中水科技H9000 V4.0系统所采用的设计思想、技术方案和施工改造详细过程;在不影响电厂正常运行的条件下,成功地实现了两套差异较大的监控系统之间平稳过渡。
This paper introduces in detail the design idea, technical scheme and construction process of the computer monitoring system of Qingbaogazhou Hydropower Plant from foreign CEGELEC system to H9000 V4.0 system of Zhongshui Science and Technology. Without affecting the normal operation of power plant , Successfully achieved a smooth transition between two sets of monitoring systems with large differences.