某综合楼建筑面积6200m~2,属于商业民宅综合用楼,自一九八九年六月开始桩基础施工。首层于同年十二月二十日动工开始主体工程施工,至1990年9月主体工程完成。1991年4月中旬开始装饰工程施工,至同年六月工地发现一层主体砌体多处出现裂缝,并且发展迅速,必须采取应急措施进行加固处理。 1.加固前情况前层纵墙砖砌体50个门窗洞口处墙垛,大多出现正向平面垂直裂缝,长达300mm,裂缝最宽处达300mm左右。北侧一层(G)轴与(40)轴相交墙垛基本压坏,
A comprehensive building construction area of 6200m ~ 2, belong to the commercial residential complex, from June 1989 began pile foundation construction. The ground floor started construction of the main project on December 20 of the same year and completed the main project until September 1990. Beginning in mid-April 1991, the construction of decorative works started. In June of the same year, a large number of cracks in the main masonry were found on the site and the development was rapid. Emergency measures must be taken to reinforce the cracks. 1. Pre-reinforcement situation The front vertical wall brickwork 50 door and window openings at the wall stack, most of them appear vertical plane vertical cracks, up to 300mm, the crack at the widest point of about 300mm. The north layer of the (G) axis intersects with the (40) axis intersects the wall stack is basically crushed,