古比雪夫水电站的工地上伏尔加河的截流工程

来源 :人民长江 | 被引量 : 0次 | 上传用户:ok_qq
下载到本地 , 更方便阅读
声明 : 本文档内容版权归属内容提供方 , 如果您对本文有版权争议 , 可与客服联系进行内容授权或下架
论文部分内容阅读
古比雪夫水电站兴建在卡玛河口下游的伏尔加河上,沙玛河湾的起点。古比雪夫水利枢纽包括有水电站,混凝土溢流坝和土坝、船闸、渠道和堤等部份。古比雪水利枢纽的建筑工程量和安装工程量如下:土方152,000,000公方,其中100,000,000公方是利用水力机械化完成的;混凝土和钢筋混凝土约7,500,000公方。在欧洲最大的河流上,于很短的时间内进行这样巨大的建筑之所以可能,是凭籍于重工业和建筑材料工业发展的成就,以及水工建设所积累的经验。保证在一年四季内各种建筑和安装工程不断地施工是顺利建筑的最重要的条件。 Gobishev Hydropower Station was built on the Volga River downstream of the Kama Estuary, the beginning of the Sharman Bay. Gubischeff Hydroelectric Complex includes hydropower stations, concrete spillway dam and earth dam, ship lock, canal and embankment. The construction and installation works for the Gubei hydro complex are as follows: 152 million square earthworks, of which 100,000,000 square meters are hydro-mechanized; and approximately 7,500,000 square meters of concrete and reinforced concrete. The huge river in Europe, in a very short period of time to carry out such a huge building is possible, is due to membership in the heavy industry and building materials industry achievements, as well as hydraulic construction of the accumulated experience. It is the most important condition for smooth construction to ensure continuous construction of various buildings and installations throughout the year.
其他文献
目的探讨新生儿肺透明膜病与先天性人巨细胞病毒(HCMV)感染之间的关系。方法选择HCMV直接早期保守区基因序列,合成两对引物,应用套式聚合酶链式反应检测了30例新生儿肺透明膜病患儿和10例新生儿非肺透明膜病患儿的肺组织石腊切片中的HCMV DNA。结果30例新生儿肺透明膜病患儿肺组织石蜡切片标本中有11例HCMV DNA阳性,阳性率为36.7%,对照组肺组织HCMV DNA均阴性。经统计学处理,二