论文部分内容阅读
1988年11丹23日~12月3日水利水电规划设计管理局会同四川省计经委在成都召开会议,审查通过了大渡河瀑布沟水电站可行性研究报告。会议认为,1983年以来,水电部成都勘测设计院及有关单位对该电站工程做了大量勘测、设计和科研工作,所提的上述报告质量良好,满足了可行性阶段要求。
1988 11 Dan 23 ~ December 3 The Planning and Design Authority for Water Conservancy and Hydropower plans to hold a meeting with the Sichuan Provincial Commission of Economic Planning and Development in Chengdu to examine and approve the feasibility study report of the Pubugou Hydropower Station in Dadu River. The conference held that since 1983, the Chengdu Survey and Design Institute of the Ministry of Electric Power and the relevant units have done a lot of surveying, designing and scientific research on the power station project. The above mentioned reports are of good quality and meet the feasibility stage requirements.