双导梁穿行式架桥机由于具有自动化高、架设跨度大、吊装质量大及工效高等优点,越来越多地被公路桥梁架设所采用。但用长度较大的大型双导梁架桥机架设跨径大、预制梁重量大、半径较小的斜坡桥时,其施工荷载、导梁的前移就位、预制梁的纵向前移运送、横向就位等都比较困难。在通梅一级公路二密河大桥施工中,通过对架桥机前支腿、前桁车横梁、中台车等关键部位进行技术改造,并采用双导梁旋转就位、后端临时支撑的方法克服了上述难题。不但缩短了工期,而且降低了造价,创造了我省双导梁穿行式架桥机架设小半径大跨径弯坡斜桥的先例。
Due to the advantages of high automation, large installation span, large lifting capacity and high work efficiency, the double guide beam walkthrough bridge machine is increasingly used by road and bridge erection. However, when the large-span double-girder bridge erecting machine is used to support the span bridge with large span, large prefabricated girder weight and small radius, the construction load, forward displacement of the guide girder and longitudinal advancement of the prefabricated girder , Horizontal position and so on are more difficult. In the construction of Tongmei Class I Highway Bridge, through the technical transformation of the key parts such as the erecting outrigger, beam of front truss, middle trolley and other key parts, Method to overcome the above problems. Not only shorten the construction period, but also reduce the cost, and created a province of double guide beam through the bridge rack set a small radius large-span curved slope of the precedent.