Abstract: the national rail traffic development rapidly, public transportation of widely used heavy escalator. Rail transit construction escalator by ladder model, underground environment, management system, interface professional, cross construction influence, and other common in construction process management in escalator have different requirements. According to the particularity, in guangzhou subway years public transportation overloaded type construction management experience escalator, summarizes the rail transit, puts forward the main escalator supervision and project management of important matters of attention, in order to improve the rail transit the escalator supervision management level and efficiency, and provide other rail traffic management reference for the same.
Keywords: rail traffic, escalator supervision, work analyzes
中圖分类号:C913.32文献标识码:A 文章编号:
全国轨道交通事业正在蓬勃发展,截止2012年,已经建成或者正在建设地铁的城市超过30个,而公共交通重载型扶梯作为在公共场合下快捷、舒适、连续的运输设备也在这种建设发展中得到广泛应用。由于受轨道交通特殊的地下环境、特殊的管理体制、接口专业多、交叉施工等方面的影响,公共交通重载型扶梯与其他普通扶梯在建设期间的管理模式、管理要求、工程的难点、重点等方面均有很大的差别。为了更好地指引轨道交通扶梯监理的管理工作,本文将结合广州地铁扶梯管理中的经验,从轨道交通扶梯和普通扶梯不同的管理要点出发,对在轨道交通建设期间,扶梯监理在各个阶段的主要工作和注意事项进行较为详细的阐述,以提高扶梯监理的管理水平和工作效率,同时可供全国其他轨道交通同行参考。
一、关于轨道交通扶梯监理的资质要求
由于在日常工程建设中并无专门的扶梯监理,因此监理公司在配置扶梯监理人员上也无认真地考究,造成部分监理人员未能胜任工作、在扶梯的建设中未能起到应有的管理和协调作用。基于扶梯属于特种设备的情况,我们对扶梯监理提出明确的资质要求:
除具有工程师以上(含工程师)技术职称和监理工程师证书,并具有5年以上工作经验,至少3年从事工程监理经验的常规要求外,我们还要求在每个监理标段配置1名具有特种设备操作证书的专业监理工程师,具有扶梯设备和操作的基本知识,并担任该监理标段扶梯监理的组长,以指导其他扶梯监理的工作。
二、轨道交通扶梯监理各阶段的主要工作和安全管理要点
1、在施工准备阶段的主要工作和安全管理要点
为保证扶梯安装工程能够顺利进行,及早办理相关手续和发现现场问题,扶梯监理要做好以下几项主要工作:
1.1 组织扶梯图纸会审工作。
在图纸会审过程中,设计人员向参建各方介绍设计意图和设计文件的要求。监理和扶梯厂家在会审前已经认真看图,核查是否有设计错误,在看图过程中需要注意的以下几个方面:吊钩的设置数量及位置、扶梯梯级到上空装修完成面的净空高、室外扶梯集水井的设置、国标中规定的扶梯与周边障碍物的距离要求等相关内容,尽量从设计阶段发现问题,减少工程实施过程中由于设计错误导致扶梯工程实施的滞后。
1.2进行现场调查,跟踪土建现场扶梯井道施工进度,并且定期检查站内站外运输通道是否符合要求。
1.3根据现场的情况及时通知扶梯厂家进行井道测量和复测工作,共同参加车站主体的移交会议并做好相关问题的记录,并且跟进扶梯井道整改工作。
1.4本阶段扶梯监理安全管理要点:
注:文章内所有公式及图表请以PDF形式查看。
关键词:轨道交通,扶梯监理,工作剖析
Abstract: the national rail traffic development rapidly, public transportation of widely used heavy escalator. Rail transit construction escalator by ladder model, underground environment, management system, interface professional, cross construction influence, and other common in construction process management in escalator have different requirements. According to the particularity, in guangzhou subway years public transportation overloaded type construction management experience escalator, summarizes the rail transit, puts forward the main escalator supervision and project management of important matters of attention, in order to improve the rail transit the escalator supervision management level and efficiency, and provide other rail traffic management reference for the same.
Keywords: rail traffic, escalator supervision, work analyzes
中圖分类号:C913.32文献标识码:A 文章编号:
全国轨道交通事业正在蓬勃发展,截止2012年,已经建成或者正在建设地铁的城市超过30个,而公共交通重载型扶梯作为在公共场合下快捷、舒适、连续的运输设备也在这种建设发展中得到广泛应用。由于受轨道交通特殊的地下环境、特殊的管理体制、接口专业多、交叉施工等方面的影响,公共交通重载型扶梯与其他普通扶梯在建设期间的管理模式、管理要求、工程的难点、重点等方面均有很大的差别。为了更好地指引轨道交通扶梯监理的管理工作,本文将结合广州地铁扶梯管理中的经验,从轨道交通扶梯和普通扶梯不同的管理要点出发,对在轨道交通建设期间,扶梯监理在各个阶段的主要工作和注意事项进行较为详细的阐述,以提高扶梯监理的管理水平和工作效率,同时可供全国其他轨道交通同行参考。
一、关于轨道交通扶梯监理的资质要求
由于在日常工程建设中并无专门的扶梯监理,因此监理公司在配置扶梯监理人员上也无认真地考究,造成部分监理人员未能胜任工作、在扶梯的建设中未能起到应有的管理和协调作用。基于扶梯属于特种设备的情况,我们对扶梯监理提出明确的资质要求:
除具有工程师以上(含工程师)技术职称和监理工程师证书,并具有5年以上工作经验,至少3年从事工程监理经验的常规要求外,我们还要求在每个监理标段配置1名具有特种设备操作证书的专业监理工程师,具有扶梯设备和操作的基本知识,并担任该监理标段扶梯监理的组长,以指导其他扶梯监理的工作。
二、轨道交通扶梯监理各阶段的主要工作和安全管理要点
1、在施工准备阶段的主要工作和安全管理要点
为保证扶梯安装工程能够顺利进行,及早办理相关手续和发现现场问题,扶梯监理要做好以下几项主要工作:
1.1 组织扶梯图纸会审工作。
在图纸会审过程中,设计人员向参建各方介绍设计意图和设计文件的要求。监理和扶梯厂家在会审前已经认真看图,核查是否有设计错误,在看图过程中需要注意的以下几个方面:吊钩的设置数量及位置、扶梯梯级到上空装修完成面的净空高、室外扶梯集水井的设置、国标中规定的扶梯与周边障碍物的距离要求等相关内容,尽量从设计阶段发现问题,减少工程实施过程中由于设计错误导致扶梯工程实施的滞后。
1.2进行现场调查,跟踪土建现场扶梯井道施工进度,并且定期检查站内站外运输通道是否符合要求。
1.3根据现场的情况及时通知扶梯厂家进行井道测量和复测工作,共同参加车站主体的移交会议并做好相关问题的记录,并且跟进扶梯井道整改工作。
1.4本阶段扶梯监理安全管理要点: