华能德州电厂Ⅲ期为2×660MW机组,分别在2002年7月和2002年10月投入生产运行。锅炉为德国BABCOCK公司生产,亚临界参数,自然循环汽包炉,单炉膛对冲燃烧,Π型布置,一次中间再热,平衡通风,固态排渣。锅炉尾部烟井分2部分,以省煤器分隔墙为界,后部烟道布置低温过热器,前部烟道布置低温再热器,在低温过热器和低温再热器的下方布置省煤器,在省煤器的下方,安装有烟气调节挡板,主要用于再热器和过热器汽温的调节。省煤
Huaneng Texas Power Plant Phase III 2 × 660MW unit, respectively, in July 2002 and October 2002 put into production and operation. Boiler for the German company BABCOCK, subcritical parameters, natural circulation drum stove, single-chamber hedge combustion, Π-type layout, an intermediate reheat, balanced ventilation, solid slag. The boiler tail silt is divided into two parts, with the economizer partition wall as the boundary, the rear flue arranges the low temperature superheater, the front part flue arranges the low temperature reheater, arranges the coal saving below the low temperature superheater and the low temperature reheater In the economizer below the installation of flue gas damper, mainly for reheater and superheater steam temperature regulation. Save coal