一、引言 大型水利水电工程的混凝土坝施工问题,往往因坝体混凝土工程量巨大而成为控制整个工程工期、左右工程投资的关键。在施工组织设计中,合理配置浇筑设备、妥善安排坝体混凝土浇筑程序以及正确预测浇筑工期都是需要认真研究解决的问题。我们以二滩双曲拱坝方案为例,应用系统分析方法对混凝土拱坝浇筑优化问题进行了研究,取得了初步成果。为使此项成果尽快完善并推广使用,特作一扼要介绍,期望得到系统工程
I. INTRODUCTION Concrete dam construction problems of large-scale water conservancy and hydropower projects are often the key to controlling the entire project duration due to the huge volume of concrete in the dam body. In the design of construction organization, it is a problem that needs to be seriously studied and solved in order to rationally dispose the pouring equipment, properly arrange the dam concrete pouring procedure and correctly predict the pouring construction period. Taking the Ertan double curvature arch dam scheme as an example, this paper studies the optimization of pouring of concrete arch dam by using the method of system analysis and obtains the preliminary results. In order to make this achievement as soon as possible to improve and promote the use of special make a brief introduction, expect to get systems engineering