我国第一项穿越沙漠的引水工程目前正在甘肃北部的腾格里沙漠紧张施工,这项名为景泰川电力提灌二期延伸向民勤调水的工程建成后,不仅充分挖掘发挥了原有水利工程的潜力,而且将使民勤县的60万亩耕地灌溉得到有效保障。总投资概算为2.46亿元的景电二期延伸向民勤调水工程已于1995年11月正式开工,主要是利用已建成的景电二期工程空闲容量和灌溉间隙,发挥现有工程设施的作用,跨流域向民勤县的红崖山水库
China’s first diversion project across the desert is currently under intense construction in the Tengger Desert in northern Gansu. After the project of extending the water from Jingtai River to Minqin for the second phase has completed its construction, it has not only fully exploited the original water resources The potential of the project will also ensure that the irrigation of 600,000 mu of arable land in Minqin County will be effectively protected. The total investment is estimated to be 246 million yuan Jing King two extension to the Minqin water diversion project was officially started in November 1995, the main is the use of the second phase has been completed Jingding free capacity and irrigation gaps, to play the existing engineering facilities The role of inter-basin to Minqin County Hongyashan reservoir