大中型水利工程项目大多采用平面闸门、弧形闸门、人字闸门、反弧门等设计,但由于工程项目存在差异,国家原有的技术标准无法囊括新工程和新情况。为保证水利工程质量,在实际施工中必须对闸门的施工技术提出高要求。文章以广西红水河桥巩水电站工程为例,对水利工程闸门的技术安装与质量控制进行了探讨。
Large and medium-sized water conservancy projects mostly use flat gate, arc gate, gib gate, anti-arc gate and other designs. However, due to differences in construction projects, the original national technical standards can not include new projects and new situations. In order to ensure the quality of water conservancy project, in the actual construction, the gate construction technology must be put forward high requirements. Taking the Hongshuiheqiao Gongshui Hydropower Station in Guangxi as an example, the article discusses the technical installation and quality control of the water conservancy project gate.