论文部分内容阅读
(截止到5月31日)1前期工作完成情况北支大桥于2009年3月份正式动工。按照“先租后征、协议动迁”的方法,沿线路桥工程于2009年7月份部分开工。在办理沿线公益林树木搬迁后,崇启通道工程(上海段)于2009年11月底全面动工。2形象进度完成情况路基施工:Ⅰ、Ⅱ、Ⅲ已于四月底完成了封层施工,ⅣV标完成封层的90%(剩余量在滩涂段)。跨线桥施工:四季公路、北沿公路跨线桥等6座公路、机耕、人行跨线桥完成主体施工,正在进行初验。水稳施工:总量108万t,完成48.3万t(其中VI—1完
(As of May 31) 1 Completion of previous work The North Branch of Bridge was officially started in March 2009. In accordance with the method of “leasing after levy, agreement relocation”, the road and bridge engineering was partially started in July 2009. After handling the relocation of trees for public welfare forests along the line, Chong Kai Passage Project (Shanghai Section) commenced construction in full by the end of November 2009. 2 Image Progress Completed Subgrade construction: Ⅰ, Ⅱ, Ⅲ completed the sealing construction at the end of April, ⅣV completed 90% of the sealing layer (the remaining amount is in the tidal flat). Flyover Construction: Four Seasons Highway, North along the highway flyover and other six roads, plow, pedestrian overpass bridge to complete the main construction, is the initial test. Water-stable construction: a total of 1.08 million tons, completed 483,000 tons (of which VI-1 finished