【世界核新闻网站2016年9月2日报道】经过六年的计划和准备,安大略电力公司(OPG)表示已“准备好执行”达灵顿核电厂的整修工作,项目预计耗资不超过128亿加元(90亿美元),将于2016年10月动工。该电厂共有4台881 MWe的坎杜(Candu)机组,均在1990—1993年间实现首次并网发电,现有许可证将在2025年前后到期。该电厂的发电量占安大略全省总发电量的约20%。安大略电力近日公布2016年上半年业绩报告,介绍了经过六年详细规划和筹备的达灵顿核电厂整修项目迄今所取得的进展。
[World Nuclear News Websites September 2, 2016] After six years of planning and preparation, Ontario Power Company (OPG) said it is “ready to implement” the refurbishment of the Darlington nuclear power plant, which is estimated to cost no more than C $ 12.8 billion (9 billion U.S. dollars) to start construction in October 2016. The plant has a total of 4 881 MWe Candu units, each with its first grid-connected power generation between 1990 and 1993, with existing permits to expire in about 2025. The power plant accounts for about 20% of Ontario’s total electricity generation. Ontario Power recently released the first half of 2016 performance report, describes the six-year plan and preparation of the Darlington nuclear power plant renovation project so far made progress.