三明钢铁厂第二炼钢车间15t×2氧气顶吹转炉于1978年元旦建成投产后,为了回收转炉煤气、充分利用能源、减少环境污染,1979年初,依靠本厂技术力量,对15t 氧气顶吹转炉的烟气净化、煤气回收系统的工艺设备进行检验、试车,摸索有关工艺系数,对原设计的一些工艺设备进行部分改造并添补必要的安全措施,于1979年4月中旬实现煤气回收一次投产成功,至今已安全运行7年整,共回
After the 15t × 2 oxygen top-blown converter of the second steel-making workshop of Sanming Iron and Steel Plant was put into operation on New Year’s Day in 1978, in order to recover converter gas, make full use of energy and reduce environmental pollution, in early 1979, relying on the technical force of our factory, Converter flue gas purification, gas recovery system for testing equipment, testing, exploring the relevant process factor, the original design of some of the process equipment to make some changes and add the necessary safety measures, in mid-April 1979 to achieve a recovery of gas production Success, has been running safely for seven years, a total of back