进行液压试验之前,管道内已经安装好的阀门需要进行正确的处理,以免影响液压试验的正常进行或避免液压试验对阀门造成损坏;同时,应尽量保留阀门在管道中,以减少阀门拆除和回装的工作量。文章根据阀门的自身特点,讨论了阀门在管道液压试验中的两类处理方法,一类是把阀门从管道中拆除,不参入管道的液压试验;另一类是把阀门保留在管道中,以开或者关的状态和管道一起进行液压试验。
Prior to the hydraulic test, the valve has been installed in the pipeline need to be properly handled, so as not to affect the normal hydraulic test or to avoid hydraulic test damage to the valve; the same time, the valve should be retained in the pipeline to reduce valve removal and back Loading workload. According to the characteristics of the valve, the article discusses two types of valve treatment methods in the pipeline hydraulic test, one is to remove the valve from the pipeline, do not participate in the pipeline hydraulic test; the other is to retain the valve in the pipeline to Open or closed state with the pipeline hydraulic test.