山西太原冯建义问:甲木器加工厂(承揽方)与乙单位(定作方)签订了一份加工承揽合同,约定甲方应于1944年6月30日以前为乙方完成105套木制门窗的定作任务,乙方应干6月30日给付酬金。但乙方因建筑工程纠纷,至1995年2月10日甲厂发生火灾使105套门】窗被烧,未领取定作物,也
Feng Jianyi, Shanxi Taiyuan Q: A processing plant (contractor) signed a processing contract with unit B (contracting party), stipulating that Party A should complete 105 sets of wooden doors and windows for Party B before June 30, 1944 Assigned to the task, Party B should pay June 30 remuneration. However, Party B was in dispute over the construction work. As of February 10, 1995, a fire broke out in the A factory and 105 sets of doors were opened. The windows were not burnt.