一、工程概况徐州矿务局义安煤矿是1972年简易投产的年产30万吨矿井,除风井外,只有一个罐笼井筒,生产环节不配套,提升能力受很大限制,影响了矿井产量的提高。鉴于该矿储量丰富,年产能力可由30万吨扩大到90万吨,决定对该矿井进行补套改造,即在原工业广场内新建一个主提升斜井(兼人行安全出口)。斜井为半圆拱形断面,净宽3800毫米,净高3024毫米,壁厚600毫米钢筋混凝土结构,坡度17度30分,掘进断面21.63米~2,净断面13.27米~2,钢筋混凝土铺底。井筒穿过冲积层240米(斜长),斜井全长1240米。冲积层部分采用降低水位法施工,获得了成功。
First, the general situation of the project Xuzhou Coal Mine Bureau of Coal Mine Safety is an annual output of 300,000 tons in 1972, an annual output of mine, in addition to the shaft, only one cage well, the production process is not complete, to enhance the ability to be greatly restricted, affecting the mine output Improve. In view of the abundant reserves of the mine, the annual production capacity can be expanded from 300,000 tons to 900,000 tons. It decided to rebuild the mine by building a new main shaft (parallel exit safety) in the former Industrial Square. Slope is semicircular arch section, the net width of 3800 mm, a net height of 3024 mm, wall thickness 600 mm reinforced concrete structure, slope 17 degrees 30 minutes, heading section 21.63 m ~ 2, net section 13.27 m ~ 2, reinforced concrete paving. Wellbore through the alluvial layer 240 meters (inclined length), inclined shaft full length 1240 meters. Alluvial layer part of the water level method to reduce construction, and achieved success.