针对静态无功优化系统仅采集、计算当前数据断面的缺陷,引入相似日负荷预测方法,对短期和超短期负荷进行预测,并进行负荷曲线合理分段,为下一个调度周期各个时段的电压无功控制提供决策依据,避免了由于负荷波动造成的各变电所电容的投切和有载主变分接头调节振荡或者不必要操作,延长设备的运行寿命。通过对某地区实际系统的应用表明,合理利用系统负荷历史数据,在线数据和预测数据,不但能满足电网电压无功优化运行的要求,而且有效减少设备的动作次数。
For the static reactive power optimization system, only the defects of the current data cross section are collected and calculated, and the similar daily load forecasting method is introduced to predict the short-term and ultra-short-term loads. The load curve is reasonably segmented to provide the voltage for each period of the next scheduling cycle Power control to provide a basis for decision-making to avoid due to load fluctuations caused by the substation capacitor switching and load with the main transformer tap adjustment or unnecessary operation, to extend the operational life of the device. The application of the actual system in a certain area shows that rational utilization of system load historical data, on-line data and forecast data can not only meet the requirements of grid voltage reactive optimization operation, but also reduce the number of operation of equipment effectively.