2010年夏天,因极端酷热,某地电网负荷达到了历史极值。在商业最为繁华和居民最为集中的市中心地带,线路过载造成的停电此起彼伏。一时间,该市地方各大论坛对供电公司的质疑声霎时高涨。面对质疑,该市供电公司对于停电原因作出解释,矛头直指征地受阻的变电站建设。在该市地方大大小小的媒体及论坛上,有一句话分外引人注目:“事实上,4年前,省电力公司就预计到今天的尴尬,批准了变电站立项来满足中心城区不断增长的负荷需求,但由于征地到不了位,迟迟无法开工,造成资源浪费,又极大地影响了工业和居民用电。”
The summer of 2010, due to extreme heat, a local power grid load reached the historical extremes. In the most prosperous commercial and residential areas in the center of the city, the line overload caused by blackouts. For a time, the city’s major forums questioned the power company’s sound suddenly rising. In the face of doubt, the city power company to explain the reasons for the blackout, spearheads directed at the blocked substation construction. In the local media and forums, large and small, there is a remark that attracts attention: “In fact, four years ago, the provincial power company predicted the embarrassment of today and approved substation projects to meet the needs of the downtown area However, due to the lack of land for land acquisition, it has been delayed to start construction, causing waste of resources and greatly affecting the industrial and residential electricity consumption. ”