摘要:随着我国经济的不断发展,很多建筑工程出于经济效益的要求,对建筑工期要求很高,很多房屋建筑工程在寒冷的冬季继续施工。而冬季由于其季节的特殊性造成施工的难度加大,施工中需注意的事项增多,因此,冬季施工应制定一套成熟的施工方案,保证施工的安全和质量。本文从房屋建筑冬季施工的特点入手,详细探讨了房屋建筑冬季重点工程施工技术应注意的问题。
关键词:房屋建筑;冬季施工;混凝土;钢筋冷拉;养护
Abstract: with the constant development of economy in our country, many construction projects due to economic efficiency requirements, the construction time limit for a project requirements is very high, a lot of housing construction project in the cold winter to continue the construction. Due to the particularity of the season and winter difficulties caused by construction, therefore, the increase in the number of matters that should pay attention to the construction of winter construction should develop a mature construction plan, ensure the construction safety and quality. From building the analysis on the characteristics of winter construction, this paper detailed discusses the housing construction should be pay attention to key project construction technology in winter.
Key words: building construction; Winter construction; Concrete; Cold-drawn steel bar; maintenance
中图分类号:文献标识码:A文章编号:2095-2104(2013)
一、房屋建筑冬季施工的特点
(一)气温低
我国冬季气温非常寒冷,尤其是我国大部的北方地区,整个冬季都会在零下度过。在如此严寒的温度下施工的难度不言而喻,很多建筑用材的保管难度、商用混凝土的制造及运输难度、材料的运送难度、钢筋焊接的难度、砌筑难度都非常大。
(二)有效施工时间短
我国处于北半球,漫长的冬季白昼短、黑夜长,而且冬季夜晚温度极低,夜晚施工几乎不可能,这就造成了冬季有效施工时间较短的特点,施工单位难以像其他季节一样有效进行施工操作。此外,冬季施工条件恶劣,建筑务工人员的工价也会随之上涨,这一因素也制约这冬季房屋施工的进行。
(三)施工人员不适,施工危险因素增加
很多施工人员习惯了正常温度下施工的各种技术指标以及施工操作。一旦到了寒冷的冬季,很多施工人员不能适应冬季施工的特点,没有掌握冬季施工的各项技术指标和施工操作章程,没有进行针对冬季房屋建筑施工特点的培训,仍然按照平时使用的老方法进行冬季施工,难免会出现这样那样的问题,给整个房屋建筑施工埋下安全隐患。
房屋建筑重点工程冬季施工技术应注意的问题
(一)混凝土工程
混凝土施工作为现代工程建设中的重要组成部分,其凝结强度以及牢固强度关系着工程的综合质量,一直被当作施工的重点来对待。由于混凝土的制作和凝结会受到气温的严重影响,所以我们在冬季施工中也应该高度关注其冬季施工技术,主要的内容有以下几点:
技术要求
冬季施工的混凝土在运输、浇筑过程中的温度和覆盖的保温材料均进行热工计算,并据此施工。拌制混凝土所用骨料应清洁,不得含有冰、雪、冻结及其他易裂物质。拌制时,先将石子与水搅拌,然后再加砂,水泥,混凝土搅拌时间不少于90s。搅拌水加热温度水温为50℃~60℃。冬季浇筑的混凝土掺用防冻剂,其受冻临界强度不得小于4.0N/mm2。混凝土冬季施工应优先选用硅酸盐水泥和普通硅酸盐水泥,水泥标号不应小于32.5R级,最小水泥用量不应小于300kg/m3,水灰比不应大于0.6,并应根据实验室配合比要求进行配料。
模板外和混凝土表面覆盖的保温层,不应采用潮湿状态的材料,也不应将保温材料直接铺盖在潮湿的混凝土表面,新浇混凝土表面应铺一层塑料薄膜或草帘子。拌制掺用防冻剂的混凝土,采用粉剂时,按要求掺量直接撒在水泥上面和水泥同时投入。配制与加入防冻剂,应设专人负责并做好记录,严格按剂量要求掺入。混凝土在浇筑前,应清除模板和钢筋上的冰雪和污垢,运输和浇筑混凝土用的容器应有保温措施。混凝土浇筑时,快浇快盖,要保持浇筑后的养护温度,如留有施工缝时,在浇筑前铺1:2水泥砂浆,随铺随浇。
2、混凝土运输
冬季运输混凝土要使用恰当的运输容器,遴选正规的商用混凝土公司。在运输的过程中,高度关注混凝土混合材料的保温,具体地从控制运输的距离、为车辆装设保温装置或者是现场直接搅拌的方式实施操作。
3、混凝土浇筑
在进行浇筑操作前,施工人员要充分了解所购混凝土抗冻方面的性能,并根据这一信息制定相应的保暖措施。
在混凝土浇筑时,应该清除模板和预埋件上面的水、冰、霜以及杂物,在必要的时候还要设置保温以及防风装置。此外值得我们注意的是,混凝土入模时的温度应该控制在10℃~20℃之间。
混凝土养护
冬施混凝土采用综合蓄热法:即混凝土配比中加入适当的抗冻外加剂,并利用加热拌制的混凝土的热量及水泥水化释放出来的热量,通过适当的保温材料覆盖,防止热量过快散失,延缓混凝土的冷却速度,保证混凝土能在正温环境下达到预期强度要求的一种方法。
(1)凝土养护采用蓄热法进行养护,混凝土的入模温度要求不低于5℃,利用这种预加的热量和水泥的水化热量,延长混凝土正温养护时间,并在冷却过程逐渐硬化,当混凝土温度降至0℃时可提前達到抗冻临界强度要求。
(2)冬施综合蓄热法,要严格控制混凝土入模温度, 不低于5℃,混凝土浇灌要连续 ,尽量缩小工作面。
(3)墙的混凝土养护
在墙的表面先挂一层黑色塑料布,在黑色塑料布外面再挂一层阻燃稻草被,既能防止混凝土内的水份蒸发,又能防止混凝土内热量的散失。
(4)冬期施工,严格监测混凝土的强度。可采用测试同条件试块的方法控制保温的拆除
时间。浇筑混凝土时,要求试验工做试块放在施工面上同条件养护,时间准确到小时,在1~2d内到试验室内试压,并将试压结果立即通知技术人员,经技术人员校对,混凝土强度达到临界强度,再通知拆除保温。
(5)垫层、底板混凝土浇筑完后,先用黑塑料布覆盖于混凝土表面, 再用2层阻燃稻草被覆盖于黑塑料布之上;竖向结构要挂阻燃稻草被, 并用铅丝扎牢,黑塑料布要有一定的搭接长度(≥300mm)且接头要相互错开。对于构件的边棱、端部和凸角要特别加强保温,新浇混凝土与已硬化混凝土连接处,为避免热量的传导损失,必要时应及早加设、加厚保温被等保温措施。
(6)混凝土养护期间测温
测温点的选择:测温孔应设置在有代表性的结构部位和温度变化大易冷却的部位,孔深为10~15cm,也可为板厚的1/2或墙厚的1/2;测温点要编号,并绘制布置图。
测温工具:采用智能型电子测温仪进行测温和人工测温相结合,利用计算机进行监测。从混凝土入模开始至混凝土未达到受冻临界强度之前,每隔2h测量一次,达到受冻临界强度以后, 应至少每隔6h测量一次,其时间为7d;人工测温时,测温仪表应采取与外界气温隔离措施,并留置在测温孔内时间不少于3min。
(二)砌筑工程
冬季施工期间的砌筑工程主要是采用抗冻砂浆法施工。
1、防冻剂的掺量应根据气温和实验配合比实施。
2、當室外大气温低于-10℃及施工上需要时,对原材料进行加热,应优先加热水,当满足不了热工计算的温度时,再进行砂子加热,但要注意水温不得超过 80℃,砂子温度不得超过 40℃,水泥不可加热,但应放在不低于 0℃得室内。
3、砌筑砂浆使用温度,当气温在-10℃以内,在-10℃~20℃时,为+10℃。搅拌好得砂浆要注意运输、存放、使用时的温度损失,最好随用随拌。
4、操作上应按照“三一”砌筑法砌筑。灰缝应控制在10mm 以内,砖砌体在当日施工完毕后,必须在表面覆盖保温材料。
5、砖上冰、霜、雪要清除,一般不得浇水,冬施工砌筑工程不可采用无熟料水泥,不得使用白灰砂浆或粘土砂浆,砂子要清除冰块。
每日砌筑后,应及时在砌筑表面进行保护性覆盖,砌筑表面不得留有砂浆。
(三)模板工程
冬施浇筑混凝土前,认真检查模板,清理模板内的冰雪。模板在混凝土达到抗冻临界强度(混凝土设计等级的30%并不低于5MPa) 并冷却到5℃后方可拆除。拆模时混凝土温度与环境温度差大于20℃时,拆模后的混凝土表面应及时覆盖,使其缓慢冷却,以防出现温差裂缝。
墙柱模板外侧挂满草帘或模板后嵌入聚苯板。冬施过程中,要注意及时清理模板上粘结的混凝土,浇完混凝土和拆模后的模板要保持干净,一定要随用随清理,以保证混凝土质量和增加模板周转使用次数。
(四)钢筋工程
冬期钢筋施工最主要的是钢筋的焊接,焊接质量的好坏直接关系到工程结构的安全。冬期进行钢筋焊接,影响因素较多,钢筋焊接前必须根据当地的施工条件、气候状况进行试焊,试焊时根据气候状况调整焊接参数及焊接工艺,焊接参数和工艺确定后,再进行试焊,试焊的焊件送实验室实验,合格后再进行批量焊接。
焊剂或焊条在冬期运输、保存过程中极易受潮,使用受潮的焊剂或焊条会造成焊接熔池中混入气体停留在焊肉中造成气孔,影响焊接接头质量。在使用焊条或焊剂时,要按说明书的要求对焊条或焊剂进行烘焙,干燥后再使用。
(五)土方工程
施工工地现场,由于原材料的运输,车辆的进出非常频繁,相关人员要保证施工现场道路的畅通无阻,及时清理垃圾。由于冬季气温很低,地面光滑程度高,所以,在施工现场要增加必要的防滑措施,保证运输的安全。另外一方面,建筑施工人员要对原有建筑物进行充分的保护,避免地基土质因为寒冷天气收到损害。在施工过程中,要尽量做到快挖快填,对相邻建筑采取侧边开挖土方操作的方法,保证地基温度,有效避免地基受冻。
结语
综上,房屋建筑冬季施工有其特殊性,低温环境会增加施工难度和各类不安全因素。因此,冬季施工要提前编制好施工方案,做好施工技术的交底工作,加强对施工人员的冬季施工培训,并重点做好几个重点分部工程的技术管理。只有如此,才能切实提高东家房屋建筑施工的技术,保证人员的安全和工程的质量。
参考文献
[1]何涛.浅谈冬季房屋建筑施工的技术措施[J].中小企业管理与科技(上旬刊),2010.3.
[2]彭燕莉,曹胜中.浅谈房屋建筑施工质量管理[J].质量管理,2008.1.
[3]肖智卿.浅谈建筑工程的冬期施工[J].青海科技,2009.6.
[4]陈瑞章.冬季房屋建筑施工概要[J].中国科技博览,2006.7.
关键词:房屋建筑;冬季施工;混凝土;钢筋冷拉;养护
Abstract: with the constant development of economy in our country, many construction projects due to economic efficiency requirements, the construction time limit for a project requirements is very high, a lot of housing construction project in the cold winter to continue the construction. Due to the particularity of the season and winter difficulties caused by construction, therefore, the increase in the number of matters that should pay attention to the construction of winter construction should develop a mature construction plan, ensure the construction safety and quality. From building the analysis on the characteristics of winter construction, this paper detailed discusses the housing construction should be pay attention to key project construction technology in winter.
Key words: building construction; Winter construction; Concrete; Cold-drawn steel bar; maintenance
中图分类号:文献标识码:A文章编号:2095-2104(2013)
一、房屋建筑冬季施工的特点
(一)气温低
我国冬季气温非常寒冷,尤其是我国大部的北方地区,整个冬季都会在零下度过。在如此严寒的温度下施工的难度不言而喻,很多建筑用材的保管难度、商用混凝土的制造及运输难度、材料的运送难度、钢筋焊接的难度、砌筑难度都非常大。
(二)有效施工时间短
我国处于北半球,漫长的冬季白昼短、黑夜长,而且冬季夜晚温度极低,夜晚施工几乎不可能,这就造成了冬季有效施工时间较短的特点,施工单位难以像其他季节一样有效进行施工操作。此外,冬季施工条件恶劣,建筑务工人员的工价也会随之上涨,这一因素也制约这冬季房屋施工的进行。
(三)施工人员不适,施工危险因素增加
很多施工人员习惯了正常温度下施工的各种技术指标以及施工操作。一旦到了寒冷的冬季,很多施工人员不能适应冬季施工的特点,没有掌握冬季施工的各项技术指标和施工操作章程,没有进行针对冬季房屋建筑施工特点的培训,仍然按照平时使用的老方法进行冬季施工,难免会出现这样那样的问题,给整个房屋建筑施工埋下安全隐患。
房屋建筑重点工程冬季施工技术应注意的问题
(一)混凝土工程
混凝土施工作为现代工程建设中的重要组成部分,其凝结强度以及牢固强度关系着工程的综合质量,一直被当作施工的重点来对待。由于混凝土的制作和凝结会受到气温的严重影响,所以我们在冬季施工中也应该高度关注其冬季施工技术,主要的内容有以下几点:
技术要求
冬季施工的混凝土在运输、浇筑过程中的温度和覆盖的保温材料均进行热工计算,并据此施工。拌制混凝土所用骨料应清洁,不得含有冰、雪、冻结及其他易裂物质。拌制时,先将石子与水搅拌,然后再加砂,水泥,混凝土搅拌时间不少于90s。搅拌水加热温度水温为50℃~60℃。冬季浇筑的混凝土掺用防冻剂,其受冻临界强度不得小于4.0N/mm2。混凝土冬季施工应优先选用硅酸盐水泥和普通硅酸盐水泥,水泥标号不应小于32.5R级,最小水泥用量不应小于300kg/m3,水灰比不应大于0.6,并应根据实验室配合比要求进行配料。
模板外和混凝土表面覆盖的保温层,不应采用潮湿状态的材料,也不应将保温材料直接铺盖在潮湿的混凝土表面,新浇混凝土表面应铺一层塑料薄膜或草帘子。拌制掺用防冻剂的混凝土,采用粉剂时,按要求掺量直接撒在水泥上面和水泥同时投入。配制与加入防冻剂,应设专人负责并做好记录,严格按剂量要求掺入。混凝土在浇筑前,应清除模板和钢筋上的冰雪和污垢,运输和浇筑混凝土用的容器应有保温措施。混凝土浇筑时,快浇快盖,要保持浇筑后的养护温度,如留有施工缝时,在浇筑前铺1:2水泥砂浆,随铺随浇。
2、混凝土运输
冬季运输混凝土要使用恰当的运输容器,遴选正规的商用混凝土公司。在运输的过程中,高度关注混凝土混合材料的保温,具体地从控制运输的距离、为车辆装设保温装置或者是现场直接搅拌的方式实施操作。
3、混凝土浇筑
在进行浇筑操作前,施工人员要充分了解所购混凝土抗冻方面的性能,并根据这一信息制定相应的保暖措施。
在混凝土浇筑时,应该清除模板和预埋件上面的水、冰、霜以及杂物,在必要的时候还要设置保温以及防风装置。此外值得我们注意的是,混凝土入模时的温度应该控制在10℃~20℃之间。
混凝土养护
冬施混凝土采用综合蓄热法:即混凝土配比中加入适当的抗冻外加剂,并利用加热拌制的混凝土的热量及水泥水化释放出来的热量,通过适当的保温材料覆盖,防止热量过快散失,延缓混凝土的冷却速度,保证混凝土能在正温环境下达到预期强度要求的一种方法。
(1)凝土养护采用蓄热法进行养护,混凝土的入模温度要求不低于5℃,利用这种预加的热量和水泥的水化热量,延长混凝土正温养护时间,并在冷却过程逐渐硬化,当混凝土温度降至0℃时可提前達到抗冻临界强度要求。
(2)冬施综合蓄热法,要严格控制混凝土入模温度, 不低于5℃,混凝土浇灌要连续 ,尽量缩小工作面。
(3)墙的混凝土养护
在墙的表面先挂一层黑色塑料布,在黑色塑料布外面再挂一层阻燃稻草被,既能防止混凝土内的水份蒸发,又能防止混凝土内热量的散失。
(4)冬期施工,严格监测混凝土的强度。可采用测试同条件试块的方法控制保温的拆除
时间。浇筑混凝土时,要求试验工做试块放在施工面上同条件养护,时间准确到小时,在1~2d内到试验室内试压,并将试压结果立即通知技术人员,经技术人员校对,混凝土强度达到临界强度,再通知拆除保温。
(5)垫层、底板混凝土浇筑完后,先用黑塑料布覆盖于混凝土表面, 再用2层阻燃稻草被覆盖于黑塑料布之上;竖向结构要挂阻燃稻草被, 并用铅丝扎牢,黑塑料布要有一定的搭接长度(≥300mm)且接头要相互错开。对于构件的边棱、端部和凸角要特别加强保温,新浇混凝土与已硬化混凝土连接处,为避免热量的传导损失,必要时应及早加设、加厚保温被等保温措施。
(6)混凝土养护期间测温
测温点的选择:测温孔应设置在有代表性的结构部位和温度变化大易冷却的部位,孔深为10~15cm,也可为板厚的1/2或墙厚的1/2;测温点要编号,并绘制布置图。
测温工具:采用智能型电子测温仪进行测温和人工测温相结合,利用计算机进行监测。从混凝土入模开始至混凝土未达到受冻临界强度之前,每隔2h测量一次,达到受冻临界强度以后, 应至少每隔6h测量一次,其时间为7d;人工测温时,测温仪表应采取与外界气温隔离措施,并留置在测温孔内时间不少于3min。
(二)砌筑工程
冬季施工期间的砌筑工程主要是采用抗冻砂浆法施工。
1、防冻剂的掺量应根据气温和实验配合比实施。
2、當室外大气温低于-10℃及施工上需要时,对原材料进行加热,应优先加热水,当满足不了热工计算的温度时,再进行砂子加热,但要注意水温不得超过 80℃,砂子温度不得超过 40℃,水泥不可加热,但应放在不低于 0℃得室内。
3、砌筑砂浆使用温度,当气温在-10℃以内,在-10℃~20℃时,为+10℃。搅拌好得砂浆要注意运输、存放、使用时的温度损失,最好随用随拌。
4、操作上应按照“三一”砌筑法砌筑。灰缝应控制在10mm 以内,砖砌体在当日施工完毕后,必须在表面覆盖保温材料。
5、砖上冰、霜、雪要清除,一般不得浇水,冬施工砌筑工程不可采用无熟料水泥,不得使用白灰砂浆或粘土砂浆,砂子要清除冰块。
每日砌筑后,应及时在砌筑表面进行保护性覆盖,砌筑表面不得留有砂浆。
(三)模板工程
冬施浇筑混凝土前,认真检查模板,清理模板内的冰雪。模板在混凝土达到抗冻临界强度(混凝土设计等级的30%并不低于5MPa) 并冷却到5℃后方可拆除。拆模时混凝土温度与环境温度差大于20℃时,拆模后的混凝土表面应及时覆盖,使其缓慢冷却,以防出现温差裂缝。
墙柱模板外侧挂满草帘或模板后嵌入聚苯板。冬施过程中,要注意及时清理模板上粘结的混凝土,浇完混凝土和拆模后的模板要保持干净,一定要随用随清理,以保证混凝土质量和增加模板周转使用次数。
(四)钢筋工程
冬期钢筋施工最主要的是钢筋的焊接,焊接质量的好坏直接关系到工程结构的安全。冬期进行钢筋焊接,影响因素较多,钢筋焊接前必须根据当地的施工条件、气候状况进行试焊,试焊时根据气候状况调整焊接参数及焊接工艺,焊接参数和工艺确定后,再进行试焊,试焊的焊件送实验室实验,合格后再进行批量焊接。
焊剂或焊条在冬期运输、保存过程中极易受潮,使用受潮的焊剂或焊条会造成焊接熔池中混入气体停留在焊肉中造成气孔,影响焊接接头质量。在使用焊条或焊剂时,要按说明书的要求对焊条或焊剂进行烘焙,干燥后再使用。
(五)土方工程
施工工地现场,由于原材料的运输,车辆的进出非常频繁,相关人员要保证施工现场道路的畅通无阻,及时清理垃圾。由于冬季气温很低,地面光滑程度高,所以,在施工现场要增加必要的防滑措施,保证运输的安全。另外一方面,建筑施工人员要对原有建筑物进行充分的保护,避免地基土质因为寒冷天气收到损害。在施工过程中,要尽量做到快挖快填,对相邻建筑采取侧边开挖土方操作的方法,保证地基温度,有效避免地基受冻。
结语
综上,房屋建筑冬季施工有其特殊性,低温环境会增加施工难度和各类不安全因素。因此,冬季施工要提前编制好施工方案,做好施工技术的交底工作,加强对施工人员的冬季施工培训,并重点做好几个重点分部工程的技术管理。只有如此,才能切实提高东家房屋建筑施工的技术,保证人员的安全和工程的质量。