河北省房山县高庄小型水电站两击式水轮机的进水方向是水平的,它所以采用水平方向进水,是与地形有关的。在其他地方就不一定采用水平进水。我们认为高庄水电站的安装步骤及方法是比较合理的。一、两击式水轮机的主要构件转动部分: 1.转子:叶片的曲面是2个圆弧组成,叶片由钢板制成,二端的挡水板由铸铁制成。采用「预铸」的方法将叶片固定在挡水板上,(在浇铸挡水板时就将叶片插入)。主轴不通过转子中心,把主轴用螺丝固定在挡水板上。
Fangshan County, Hebei Province, Gaozhuang small hydropower station two-stroke turbine inlet is horizontal, so it uses horizontal water, is terrain-related. There is not necessarily horizontal watering elsewhere. We think that the installation steps and methods of Gaozhuang Hydropower Station are reasonable. First, the main components of the two-stroke turbine rotating parts: 1. Rotor: blade surface is composed of two arcs, blades made of steel, the two ends of the flap made of cast iron. The “pre-cast” method is used to attach the blade to the flap, which is inserted when the flap is cast. The spindle does not pass the center of the rotor, the spindle screwed to the flap.