论文部分内容阅读
2012年9月底,云南电网公司对越送电218.4亿千瓦时,累计电力贸易额近10亿美元。据悉,截止2010年,公司累计对越送电55.29亿千瓦时,与2009年相比增长34.90%,完成2010年对越送电指标43.6亿千瓦时的126.82%,2011年,对越送电累计电量突破200亿千瓦时大关。目前,公司通过2个电压等级、4条通道共6回线路向越南北部的老
By the end of September 2012, Yunnan Power Grid Corporation sent more than 21.84 billion kwh electricity to Vietnam and the cumulative electricity trade volume was nearly 1 billion U.S. dollars. It is reported that as of 2010, the company accumulatively sent 5,529,000,000 kilowatt hours to Vietnam, an increase of 34.90% over 2009, completing the 2010 delivery target of 4.36 billion kilowatt hours to 126.82%. In 2011, Electricity exceeded 20 billion kwh mark. At present, the company through two voltage levels, 4 channels a total of 6 lines to the old northern Vietnam