长岭炼化2014年大检修工作中,物资供应处在全力以赴确保物资供应的同时,还要负责废旧物资的回收处置任务,做到了保供、回收双管齐下,较好地完成了阶段性工作。2014年大检修时间的提前,给物资供应的保供工作带来了前所未有的挑战,特别是面对设备催交工作时间紧任务重,长岭炼化供应处积极制定驻厂催交方案,正月十五还没有过完,就立即派出四路人员驻厂催交;3月份通过对检修物资的对接,详细掌握4月前到不了货的物资,组织以区域为主、供应处领导带队,机动处、工程处、科技开发处等相关部门领导、技术人员共同参与的7
Changling refinery in 2014 overhaul work, materials supply office in full power to ensure material supply, but also responsible for the recycling of waste materials disposal tasks, so as to protect the supply, recycling a two-pronged approach to better completion of the phased work . Advance maintenance time in 2014 has brought unprecedented challenges to the supply of material supply, especially in the face of urgent task of equipment reminder work time, Changling refinery supply department to actively develop the plant to submit proposals, the first month Fifteen has not been completed, immediately sent four officers in the plant reminder; in March through the docking of maintenance supplies, a detailed grasp of the goods until 4 months ago to the goods, the organization of regional-based, led by the supply office, Mobile Division, Agency, Science and Technology Development Office and other relevant departments leaders, technical staff to participate in the 7