一、建设工程施工合同认定无效的三种情况 1、承包人未取得建筑施工企业资质, 或者超越资质等级的;2、没有资质的实际施工人,借用有资质的建筑施工企业名义的;3、建设工程必须进行招标而未招标, 或者中标无效的。但在司法实践中:一是建设工程施工合同无效,但建设工程经竣工验收合格, 承包人请求参照合同约定支付工程价款的,应予以支持。二是建设工程施工合同无效,且建设工程经竣工验收不合格的, 按照以下情况分别处理。 (1)修复后的建设工程经竣工验收合
First, the construction of the construction contract was found invalid three cases 1, the contractor did not get the qualification of construction enterprises, or exceed the qualification level; 2, the actual construction of qualified workers, borrow qualified construction companies in the name of construction; 3, Construction projects must be tender without bidding, or the successful bid is invalid. However, in judicial practice, one is that construction contracts for construction projects are invalid, but construction projects that have passed the final inspection and acceptance and the contractor requests for the payment of the construction cost with reference to the contract shall be supported. Second, the construction contract is invalid, and the construction project fails to pass the final acceptance, it shall be dealt with separately according to the following conditions. (1) After the repair of the construction project by the completion of acceptance