葛洲坝水利枢纽第一期工程投入运行的第一年,1981年7月长江上游发生建国以来特大洪峰,入库流量达72,000秒立米,宜昌流量70,800秒立米,相当于一期工程的校核流量71,100秒立米。1982年2月枯水期出现了最小通航流量3,240秒立米,接近设计枯水流量3,200秒立米。1982年汛期库水位蓄至63米左右,最大流量为59,300秒立米。1983年汛期,为提高通航发电效益,库水位在64.5米以下运行,最大流量为53,300秒立米。这些条件使葛洲坝第一期工程经受了全面考验。现就工程运行近三年来的实际情况,简述如下:
The first phase of the first phase of Gezhouba Project was put into operation. In July 1981, there was a huge flood peak since the founding of the upper reaches of the Yangtze River. The inflow volume reached 72,000 seconds and Yichang traffic was 70,800 seconds. It corresponded to the check flow of the first phase project 71,100 Seconds of meters. In February 1982, a minimum navigable flow of 3,240 seconds was observed during the dry season, approaching the designed dry flow of 3,200 seconds. The reservoir water level in flood season in 1982 was about 63 meters, and the maximum flow rate was 59,300 seconds. In the flood season of 1983, in order to improve the efficiency of navigation and power generation, the water level of reservoir operated below 64.5 meters and the maximum flow rate was 53,300 seconds. These conditions make the first phase of Gezhouba project fully tested. Now on the actual operation of the project over the past three years, summarized as follows: