论文部分内容阅读
我公司于1976年接受山东体育馆施工测量任务,配合进行各个施工阶段所需要的测量工作。在工程实践中与设计和施工部门紧密配合,使该项工作圆满完成,并取得良好的效果。现就施工中框架、柱吊装,大型钢网架拼装和网架整体同步提升以及有关变形观测等测量工作简述如下,供参考。由于我们对这方面的测量是初次接触,加之水平有限,不妥之处在所难免,望批评指正。 (一)工程概况山东体育馆建筑面积14370平方米,檐口高23.3米,平面呈矩形,东西宽69.7米,南北长78.1米,容纳8200座位。东西两侧为予制钢筋混凝土双柱框架,柱距3.5米,柱长26.2米,框架间距5.7米,全长74.1米。
In 1976, our company accepted the construction survey mission of Shandong Stadium, and cooperated with the measurement work required in each construction stage. In the engineering practice, it closely cooperates with the design and construction department to complete the work and achieve good results. The following is a brief description of the measurement work on frame, column lifting, large-scale steel grid assembly and grid synchronization and related deformation observation during construction. Since we are making initial measurements in this respect and the level is limited, it is unavoidable that we are not comfortable. We hope to criticize and correct me. (I) Project Overview Shandong Stadium has a building area of 14,370 square meters, a mouthful of 23.3 meters high, a rectangular plane, 69.7 meters wide from east to west, and 78.1 meters long from north to south, and it accommodates 8,200 seats. The east and west sides are prefabricated reinforced concrete double-column frames with a column spacing of 3.5 meters, a column length of 26.2 meters, a frame spacing of 5.7 meters and a total length of 74.1 meters.