实践表明,应用网络图来安排计划和控制工程进度的效果很好。1985年以来,我厂在安排成套设备的汁划大修及车间设备的集中时间检修,都采用这项技术。 1.网络图计划的形成 过去编制大修计划,往往只把修理的重要内容、完成口期列成表格。工序之间的交叉环节、进度要求、人力安排等事前反映不出逻辑关系,不利于抓关键。在平行或交叉作业中,由于事前估计不足,就会产生忙乱,造成指挥者被动的局面。我厂每次大修都成立指挥部,要求以网络计划图指导大修
Practice has shown that using network diagrams to schedule and control project progress works well. Since 1985, our factory has adopted this technology in arranging the overhaul of complete sets of equipment and the centralized maintenance of workshop equipment. 1. The formation of the network map plan In the past, the preparation of the overhaul plan often included only the important contents of the repair and the completion of the port period. Intersections between processes, progress requirements, manpower arrangements, etc., can not reflect the logical relationship in advance, is not conducive to grasping the key. In parallel or cross-operations, due to inadequate pre-estimation, there will be a hectic order and a situation in which the conductor is passive. Every time the overhaul of our factory is established, the headquarters is required to guide the overhaul with the network plan.