陕西省汉江钢铁厂2号高炉(380m~3)在省政府、省冶金局的大力支持下,经过五冶等施工单位的共同努力,已于1994年7月29日建成投产,当日就顺利地生产第一炉合格生铁。新建的汉钢2号高炉是目前映西省高炉之首,整个系统具有以下几个特点。 1.高炉本体设计趋于合理高炉采用大框架自立式炉体结构;冷却系统形成单独高压软水闭路循环,
No.2 blast furnace (380m ~ 3) of Han River Iron and Steel Plant in Shaanxi Province was put into operation on July 29, 1994 with the strong support of the provincial government and the provincial Metallurgy Bureau and the joint efforts of construction units such as Wuye and so on. Production of the first furnace qualified pig iron. The new No. 2 blast furnace of Hangang is the first blast furnace in Yingxiu Province. The whole system has the following features. 1. Blast furnace body design tends to be reasonable Large blast furnace using a free-standing furnace structure; cooling system to form a separate high-pressure soft water closed loop,